Monday, May 7, 2012

WE HAVE MOVED IN


It has been a while since I haven´t updated my blog. Though quite a lot of things have happened and that´s the reason. In fact I have been busy to get new house ready while preparing moving from old house at the same time. In evenings I didn´t have any more time to update my blog. But yes, IT`S DONE ! We have moved into our new house 7th of April. MANY THANKS to all our friends who came to help with moving. All the finishing’s are not ready yet and there is still quite many little details to do but it´s already few weeks we are living here. And I can say that we are HAPPY !   

Photo of the day (outside)
and here inside photo



Sunday, February 5, 2012

Snowy landscape from building site


The ground has covered by snow and the view was almost like in Finland. The interior works proceed and main distribution board has assembled… But we have still no power. I started to assemble floor boards to upstairs.


Tuesday, January 17, 2012

Surface of cast on floor

This morning has done the surface of cast on the floors. The drying is slow during the winter season, so we have to wait 5-6 weeks before tiling work



Monday, January 9, 2012

Work from outside

Photo of the day. There is missing only a few finished works from outside. 



Friday, January 6, 2012

Underfloor heating has installed


A little holiday break because the Christmas is over. The plumber and the electrician has continued their work. The gas fire and underfloor heating has installed. The water is running but electric not.

Wednesday, November 30, 2011

Roofing tiles


The roofing tiles has installen and log house has covered in weather-protected. This comes at a good moment because the weather forecast does not bode well for the next few days the weather...



Tuesday, November 29, 2011

The roof is ready


Here is the photo the Day. The roof installation is progressing well. The electrician also has started, and Saur (water utility) is digging a plot of land at the entrance, so enough people on site.



Tuesday, November 15, 2011

The roof building continues


Picture of the Day. Roofing is fully inserted, as well as the first fascia boards.

Sunday, November 13, 2011

Windows


The felt under the roofing felt and the first windows has installed.

Friday, November 11, 2011

Details


Here are some details of the nailers and the windows installation to the log frame.



Wednesday, November 9, 2011

Roofing


Fibre boards + ventilation batten + felt under roofing felt installation



Monday, November 7, 2011

Friday, November 4, 2011

Roof structure


The log frame of the installation is finished and the roof structure began.



Thursday, November 3, 2011

Construction site meeting


It is time to keep the construction site meeting. No negative comments! Except this week we have lost two working days: Monday due to bad weather, and Tuesday was a public holiday.

Wednesday, October 26, 2011

Second truck



We have unload the second truck and house construction is progressing.